A Senate panel pressed Oracle Health and VA on how the EHRM contract ceiling climbed from $10 billion to $27 billion without Congress knowing, as GAO puts the lifecycle bill at $56.5 billion.

The Department of Veterans Affairs' electronic health record modernization contract ceiling with Oracle Health rose from $10 billion to $27 billion — a $17 billion increase that landed in August, largely without Congress knowing. On Wednesday, the Senate Veterans' Affairs Committee demanded to know how.
Oracle Co-CEO Mike Sicilia and Neil Evans, program executive director of VA's EHRM Integration Office, gave the panel the same core answer: the size, scope, timeline and the product itself have all changed, so the price had to change too.
"I'm not here to declare victory," Sicilia told the committee. "I'm also not here to say that everything is perfect with the system, but the scope of the system, the scale of the system has changed dramatically."
How did the $17 billion increase happen?
In prepared remarks for Thursday's House Veterans' Affairs Committee hearing, Sicilia said that over two months this summer Oracle proposed an $18.5 billion increase, which negotiators then cut to just under $17 billion before it was made official in August.
The drivers, according to the witnesses:
- A changed deployment timeline
- Added work that Evans said VA originally planned to take over but "has since realized that it is better for Oracle to continue managing"
- New requirements drawn from lessons learned in earlier rollouts
Sicilia also cited COVID-19 pandemic-related delays, customizations and "inadequate infrastructure from Cerner that impacted system stability." Cerner, the original contractor, was acquired by Oracle in 2022.
Sen. Thom Tillis, R-N.C., called the project's trajectory "all the hallmarks of a failed execution" — an execution problem, not a platform problem. "Nobody can rationalize a fourfold increase in the cost of a project without somebody's head rolling," he said, adding he could "create a Kalshi bet" that Oracle would return for money beyond the $37 billion full lifecycle cost — "and I'd put a lot of money on it."
What about Sicilia's 2022 cost-absorption pledge?
In 2022, Sicilia promised Oracle would absorb costs above the original $10 billion ceiling tied to "performance or workflow" issues. On Wednesday he called that a "sincere commitment" that remains, born of a "desire to be the best partner that we could be." He said Oracle has absorbed "many" items, including stabilizing the system, moving it to Oracle's cloud, and improving performance and workflows.
The technical footprint has more than doubled: the system was designed for 85,000 concurrent users and now must serve 195,000, while interfaces grew from about 60 to about 190. Pricing stays the same, Sicilia said, labor costs are up a few percent, and the deal includes free access to clinical artificial intelligence.
"The sheer amount of scope increases and the two-year pause could not have been anticipated at that time," Sicilia said. "We understand Congress has to decide the value and whether to continue investing taxpayer dollars."
What does the full lifecycle bill look like?
Carol Harris, the Government Accountability Office's director of IT and cybersecurity, put the numbers plainly: $37.2 billion to go live at all 170 sites by 2031, plus $19.3 billion to operate and sustain the system for another decade — a total of $56.5 billion. At a Sept. 2 House hearing, VA Deputy Secretary Paul Lawrence had estimated about $11 billion for sustainment, roughly $48 billion total.
Harris said GAO has waited over a year for the underlying analysis behind VA's cost estimate. When Evans noted there was an agreement to provide the documentation, Chairman Jerry Moran, R-Kan., cut in: "Why do you need an agreement? Just do it."
Evans defended the estimate as "informed by predictable and now validated real-world costs," adding that VA has "high confidence" it can finish deployments within $37.2 billion and that the figure was compared against an independent lifecycle estimate completed in 2022. "It becomes much easier to project what the long-term costs are when you have a clear, stable product," he said.
Was Congress deliberately kept in the dark?
Ranking member Sen. Richard Blumenthal, D-Conn., said he was "troubled" that Congress learned of the ceiling hike through news reports. Evans replied: "There was not an intentional decision to not notify Congress." He said he first understood the magnitude of the cost rise in September 2025, when full lifecycle costs were shared with the committee.
Evans said the system is stable "from a technical standpoint" — a full year without a complete outage and more than 13,000 improvements driven by user feedback. VA is pushing for 26 more site deployments next year, but Blumenthal insisted future rollouts must not follow an "arbitrary schedule" set by political leadership or Oracle pressure, and "must be contingent on VA demonstrating the program's readiness." Clinician feedback on the latest deployments, he noted, has reportedly been generally positive.
Moran closed by thanking the witnesses for the "progress" in modernizing the record system — even though, he said, "concerns remain."