Steamship Authority Spends $1.6M of $2.4M Budget on Reservation System
General manager Alex Kryska told Inspector General Jeffrey Shapiro the ferry line has spent $1.6 million of $2.4 million budgeted, with total costs now projected at $11.2 million.

The Steamship Authority has spent $1.6 million of the $2.4 million budgeted to implement its new reservation system, general manager Alex Kryska disclosed in a Nov. 10 letter responding to state Inspector General Jeffrey Shapiro, who had asked in October for updates and cost breakdowns on the delayed booking program.
The system is being built by E-Dea, an Italian firm with ferry industry experience. Kryska wrote that about $3.3 million of the total $5.7 million E-Dea contract covers software licensing and hosting through 2030. The total implementation cost — including staff training, integration with the rest of the Steamship Authority's information technology, and hardware such as ticket scanners — is expected to reach $11.2 million, inclusive of the E-Dea contract.
Only two line items have exceeded their initial estimates so far, according to the letter:
- The bulk shipping portal, now expected to cost $858,555, about $126,000 over its initial budget.
- Network equipment, at $650,000, or $190,000 over budget.
What prompted the inspector general's review?
Shapiro's concerns followed his highly critical 2025 report on the ferry line's plans for a new website. That project suffered multiple cost overruns and delays before officials paused it to concentrate on the reservation system. In the earlier report, Shapiro faulted management for not keeping the board informed and said the board was not asking management enough questions.
Kryska outlined the changes made since. The Authority has formed several subcommittees to strengthen oversight, and several officials have taken classes with the inspector general's office. Overruns on the reservation system have been relayed to the board, and updates are provided regularly at the ferry line's public meetings.
What is the rollout schedule?
E-Dea is scheduled to deliver a booking system for the high-speed Nantucket ferry next month. Testing would run through January, with a go-live date of Feb. 23. The ferry line chose the fast ferry first because passenger-only tickets are simpler.
Public vehicle bookings on the new system are projected to start in July 2027, with terminal scanning by November 2027, according to the letter.
Several factors drove the delays, Kryska wrote. Many of the Authority's reservation policies were either unwritten or inconsistent, prompting a formalization process. Several ticket programs — Headstart, excursion, bulk freight, the blue line and standby on Nantucket — are unique to the Steamship Authority. A wide range of existing data, including coupon books, open tickets and gift card balances, must be ported to the new system. Ferry terminals need network, cabling and Wi-Fi upgrades, and staff require adequate training time. E-Dea itself has been late or required fixes along the way, Kryska added.
"The IT Executive Steering Committee continues to review the project to determine the best course forward," he wrote. "A responsible schedule must come out of that review rather than precede it, and we will continue to report the project timeline at our public meetings."
What happens to the old system and the shelved website?
The existing system continues to handle all reservations and will be online when summer 2027 bookings open — the most coveted reservation window of the year.
Kryska defended the previously shelved website project as integral to the new system. "We cannot overstate this: the protracted monetary investment in the website redevelopment project, while subject to the deficiencies your office found, was not for naught – the website that was built in that project is functional, and is already integrating with the new reservation system," he wrote.
Who will manage the project going forward?
The letter also addressed project management policies and the inspector general's concern that senior staff, including the treasurer and chief operations officer, were spending extensive time on the reservation system despite other duties. Kryska agreed with the point and said the Authority is recruiting for an internal project management office led by a certified project manager.
"Once the Project Manager is on staff, the Authority will have its own capacity to manage this and future projects, and senior staff involvement will be limited to decisions and approvals within their responsibilities," he wrote.
In recent public meetings, Kryska has expressed frustration with the delays and raised the potential for an outside assessment of the work. The Authority welcomed a meeting with the inspector general, and public community meetings are scheduled over the coming week; one on the Vineyard is set for Tuesday at 5 p.m. at the Hebrew Center in Vineyard Haven.
Kryska closed the nine-page letter on a conciliatory note. "The report has been a useful roadmap for the Authority," he wrote. "We remain committed to the accountability and transparency that the public expects of us. Thank you again for your work and for your engagement on these important matters.
Source: Google News · Government Ethics & Oversight
Rebecca Stone
Show full bio
Market editor covering companies, deals and strategy in Civil Service News is the daily trade press at Civil Service News.